Tag Archives: power

City Light to remove tall pole, lines near 12th and Stevens

Utility poles in a row on S. Stevens St. Photo by Wendi.

Utility poles in a row on S. Stevens St. Photo by Wendi.

The power lines and tall poles that have concerned neighbors in the vicinity of 12th and Stevens will be changed starting next week. City Light crews will install new utility poles along S. Stevens St., as well as replacing the 71-foot pole at 12th Ave. S. and S. Stevens with a 55-foot pole. Additionally, one circuit of power cables will be moved underground to reduce view impacts in the area.

The work will begin on June 13 and continue until September.

The changes are the culmination of two years of discussions between Beacon Hill residents and City Light after a new power circuit was added to the Hill to support Link Light Rail and expected future demand. When the large poles and new wires went in, neighbors in the area of 12th and Stevens found the views from their homes were affected. Neighbors also expressed concern about the impact of the poles and power lines on the nearby 12th Avenue S. Viewpoint park. Over 100 neighbors signed a petition asking that the poles be removed.

Previous posts about the poles/power lines are here:

The power lines in question at 12th and Stevens. Photo by Wendi.

These power lines affect views for neighbors at 12th and Stevens. Photo by Wendi.


View S. Stevens St. power poles in a larger map. The blue line marks the location of the power poles on S. Stevens Street. The green area is the 12th Avenue Viewpoint park.

Power lines/poles subject of Wednesday meeting with City Light head Carrasco

Tall poles like this one are frustrating neighbors along South Stevens Street in North Beacon Hill. Photo provided by Anne Marie Harrington.
Tall poles like this one are frustrating neighbors along South Stevens Street in North Beacon Hill. Photo provided by Anne Marie Harrington.
As we mentioned last week, Seattle City Light Superintendent Jorge Carrasco will be meeting with all interested neighbors this Wednesday, December 9, from 7:00-9:00 pm at the Jefferson Community Center to discuss the new power lines going up the west side of Beacon Hill and the new higher poles running along South Stevens Street.

Neighbors in the 12th and Stevens area have been protesting the new lines and poles since they appeared last summer. They are concerned about the impact of the poles and lines on views and property values for houses in the area, and the impact on the nearby 12th Avenue Viewpoint park. About the park, neighbor Judith Edwards tells us “The tall pole and power lines are your first visual impression… Though the power lines have a great visual effect on the 12th Ave/Stevens St. neighbors, their impact on the park, which is a Beacon Hill landmark, is more than disturbing.”

Over 100 neighbors have signed a petition asking that the poles be removed.

These power lines affect views for neighbors at 12th and Stevens. Photo by Wendi.
These power lines affect views for neighbors at 12th and Stevens. Photo by Wendi.


View S. Stevens St. power poles in a larger map. The blue line marks the location of the power poles on S. Stevens Street. The green area is the 12th Avenue Viewpoint park.

Here are more photos of the power poles near 12th and Stevens, provided by Dulcie Claasen, Nick Papini, and Anne Marie Harrington.

power poles 021
power poles 013 Continue reading Power lines/poles subject of Wednesday meeting with City Light head Carrasco

City Light’s Carrasco pitches alternative for unsightly power lines

“We feel terrible that the community was made to feel like we didn’t take enough time to bring you into the assessment of this project.”

Addressing a fairly large crowd of 30-40 people including many new faces at the October NBHC meeting last week, Seattle City Light Superintendent Jorge Carrasco came to discuss the impact that new higher power poles and thicker cables have had on neighbors near 12th Avenue South and South Stevens, where new lines have been installed to supply additional power for Sound Transit and anticipated load growth in Rainier Valley, on Beacon Hill, and Capitol Hill.

Mr. Carrasco first learned of the problems via email shortly after the new lines went up. He admitted that, while there was good engineering work done on the project, a community outreach component was not included, and that work is being performed internally at City Light to determine why a project of this size was done without input or feedback from the community. He has asked their engineering department to require that affected communities be contacted and a communication strategy be implemented before final designs are implemented for any future projects. This process, however, is not yet finalized.

With large towers and cables going up the western bluff and along Stevens Street from 12th to 15th Avenue, design issues included soil stability issues, and whether or not lines could go underground. Among possible overhead wiring implementations, multiple cost alternatives were looked at. This one was chosen because other options included a mid-slope pole partway up the hillside. A mid-slope pole would have meant maintenance access issues for City Light, so they engineered around it, pulling the lines up higher and using stouter poles at the top and bottom of the slope.

When asked why the Sound Transit tunnel was not used for the power lines, Mr. Carrasco mentioned concerns from Sound Transit as well as within City Light about having these general purpose power lines running alongside transit power lines. If there were a fire in the tunnel, it would not only damage train power but also likely cut power to a big chunk of Rainier Valley and Beacon Hill. Additionally, access for maintenance and repair would require working around the transit schedule.

A buried cable option was not pursued not only due to its expense in construction and maintenance, but also because, as a utility, City Light is actually restricted from spending money for non-utility use. If undergrounding is pursued for aesthetics, the city has to chip in.

“We’re not punting on this project.”

Along the line path, there are currently sets of double-poles. Many of these are there because another utility is still using the old pole. Mr. Carrasco said that by the end of this* week, the cable television wires should be removed, bringing seven poles down. The remaining poles include four Qwest poles which City Light doesn’t have authority to address, but they are in contact with Qwest to get them removed as well. (* From my notes, I’m fairly confident Mr. Carrasco said this week, but Mike Eagan from City Light commented that they won’t be gone until the end of next week. Thanks for the clarification, Mike! –Jason)

As for remediation to the view blockage for neighbors nearby, a mid-slope pole alternative will be reconsidered. With a mid-slope pole, the pole at the top of the hill could be about 20 feet lower, however the cables would be the same thickness and run in the same number. Mr. Carrasco estimated that this change could be done fairly quickly, being completed within a month and a half to two months after work begins. This is only an option they’re prepared to look at, and City Light is interested in discussing it further, setting up another meeting, bringing some concept photos, etc. The ballpark expected cost of this alternative is about $200,000 and would be using the same cable, adding a mid-slope pole, and swapping out a shorter pole at the top of the hill. Not addressed (and seemingly not well understood by City Light when brought up during the Q&A by neighbors) is what would happen with the new, higher poles now on the plateau between 12th and 15th.

Streetlight replacement also came up during the nearly hour-long conversation with Mr. Carrasco. A process of “group re-lamping” is underway in quadrants city-wide, and currently on Beacon Hill. Group re-lamping involves changing out all of the streetlights in an area at once, instead of addressing lights one at a time as they fail. This process allows for replacement in bulk every 4-5 years. The process is expected to be complete here by November 1.

Judith Edwards, NBHC Chair, is working to schedule a follow-up meeting with Mr. Carrasco and City Light. We’ll keep you posted when the meeting has been scheduled.

If you attended the meeting or have insights or opinions to share, we’d love to have you join the discussion at the linked Forum topic, or leave them here as comments on this article.

Neighbors protest power lines; City Light responds

These are the new power lines on the west side of Beacon Hill. Photo by Wendi.
These are the new power lines on the west side of Beacon Hill. Photo by Wendi.
The Seattle Times revisited the power line controversy on northwest Beacon Hill today, including a photo of neighbors Heather DeRosier, Carole Swanson, and Joan Habu standing underneath one of the new poles with a “Take Them Down!” protest sign. The new, thicker power lines, with taller poles, were installed a few weeks ago near South Stevens Street and 12th Avenue South.

Neighbor Frederica Merrell recently sent a letter of complaint about the power lines to Seattle City Light Superintendent Jorge Carrasco, asking, among other things, “why didn’t they bring the power in from below and run the lines through the tunnel, putting them under the freeway instead of draping them in the open where they will face wind and weather?” and received the following response:

Thank you for your note about the electrical service upgrade in Beacon Hill.

Seattle City Light installed an additional set of power lines to provide service for Sound Transit’s light rail trains, electrified buses and growing energy needs in the Rainier valley. The utility spent about three years reviewing possible routes and designs to deliver this needed service upgrade. While we try to limit the impact of such projects on the surrounding neighborhoods, safety for residents and our workers, reliability of the electric supply, and cost are important considerations as well.
Continue reading Neighbors protest power lines; City Light responds

Power lines obscuring some sight lines for neighbors on the hill

From the right angle, these power lines prevent a clear view of the towering office buildings downtown. Photo by Wendi
From the right angle, these power lines prevent a clear view of the towering office buildings downtown. Photo by Wendi
Several local media outlets have picked up a story of some neighbors on the far-west edge of the hill whose views have become scarred due to taller power poles with thicker power lines, purportedly installed by Seattle City Light at the behest of Sound Transit to accommodate the power requirements of the light rail station.

Beacon Hill neighbor Roger Pence, who works with Sound Transit, said on the mailing list:

…these power lines have nothing to do with Sound Transit. We didn’t know they were going up either! This is a “betterment” project entirely the doing of Seattle City Light.

Later reports indicate that City Light upgraded the service to power trolley buses and in expectation of increased demand in Rainier Valley.

(Tangentially, I noticed the trucks on Stevens between 12th and 13th yesterday morning, and when I called City Light to inquire about them , I was told it they were performing sewer work. “TV sewer inspection.” Odd. Updating with links as they appear.)